Periodic maintenance 67
Fire alarm and suppression system
Component to be inspected Task Frequency Capable Party
Full system functional check
Inspect and perform a functional
check of the system.
As required by
local code
Licensed fire safety
contractor
—
Inspect and test fire panel
battery backup system.
Bi-annually Licensed fire safety
contractor
—
Inspect and test VESDA power
supply.
Quarterly Licensed fire safety
contractor
—
Inspect the VESDA pipe
network.
Bi-annually Licensed fire safety
contractor
—
Inspect the VESDA filter. Annually Certified facilities
personnel
—
Conduct a VESDA pipe integrity
smoke test.
Annually Licensed fire safety
contractor
—
Check the VESDA pipe flow. Annually Licensed fire safety
contractor
—
Clean the VESDA sampling
points.
Every 2 years Licensed fire safety
contractor
—
Flush the VESDA pipe network. Every 2 years Licensed fire safety
contractor
—
VESDA system air
sampling/smoke test
As required by
local code
Licensed fire safety
contractor
—
Suppression system test As required by
local code
Licensed fire safety
contractor
—
Fire-pull visual and operational
inspection
As required by
local code
Licensed fire safety
contractor
—
Fire strobe and horn visual and
operational inspection
As required by
local code
Licensed fire safety
contractor
Generator (if applicable)
Component to be inspected Task Frequency* Capable Party
Generator
Visual inspection of the generator Quarterly HP and certified
facilities personnel
—
Oil change Annually HP
—
Oil filter change Annually HP
—
Oil analysis Annually HP
—
Fuel filter change Annually HP
—
Coolant freeze point and
inhibition check each time the
generator is viewed
— HP