HP Performance-Optimized Datacenter, 12 m (40 ft) User Guide

Installation 15
1.
Verify that the HP POD, transformer, and switchboard are in the final locations.
NOTE: The following steps detail the connection procedure for a non-redundant power
installation. If you are installing your HP POD for redundant power, you will have connections
to two transformers and two switchboards.
2. Make the power connections.
a. Connect the main power leads from your facility to the transformer (1 to 2).
Each connection is labeled with colored tape, according to local standard requirements.
b. Connect the transformer to the switchboard (2 to 3).
c. Connect the three 3-inch flexible conduits from the switchboard to the junction box on the HP
POD (3 to 4).
Each connection is labeled. Two of the conduits power the electrical busway breakers, and one
powers the house panel.
3. Turn on facility power.