HP Performance-Optimized Datacenter, 12 m (40 ft) User Guide
Installation 16
4.
Close the required breakers on the switchboard.
5. Close the main breaker in both of the house panels on the exterior of the HP POD.
6. Close the remaining breakers in the house panel, following the panel schedule on the inside of the
house panel.
NOTE: If you are installing a high density HP POD, you must also close the main breaker in
the electrical busway 3 panel.
7. Close the main breakers in the electrical busway panels.