HP Performance Optimized Datacenter 240e North America (Adiabatic) Maintenance and Service Guide

Maintenance 44
Component to be inspected Task Frequency Capable party
POD shutdown required
Conduct torque checks on the
following:
Main, critical IT, house, and
mechanical cooling power
feeds
Electrical panels, breakers,
and disconnects
Busway end feeds and drop
box locking mechanism (bolt)
Annually
Licensed electrician
Grounding
Test grounding system resistance
with the ductor method.
Every 2 years Licensed electrician
POD shutdown required
Test the torque of the ground and
grounding connection/lug located
internal of each electrical panel.
Clean and re-tighten as needed.
Every 2 years Licensed electrician
Test the torque of the service
entrance grounding
ground-rod/ground well and
grounding connection/lug located
external on the POD. Clean and
re-tighten as needed.
Every 2 years Licensed electrician
POD shutdown required
Test the torque of the service
entrance ground connection/lug
located on switchboard (or
landing location). Clean and
re-tighten as needed.
Every 2 years Licensed electrician
Rack bonding
Test the torque of the grounding
system bonding jumpers that
connect racks to the POD structure
and rack to rack. Clean and
re-tighten as needed.
Every 2 years Licensed electrician
POD section bonding
Visually inspect internal
grounding/bonding connections
between the IT-A, hot aisle, and
IT-B sections. Clean and re-tighten
as necessary.
Quarterly Licensed electrician/
Qualified personnel
Circuit breakers
Test the operational panel breaker
(open and shut).
Annually Licensed electrician
LLS inspection of the following:
Breakers
Disconnects
Motor starters
Fuse holders
Quarterly
Licensed electrician/
Qualified personnel
Test the breaker faults for all
breakers ≥ 250AF.
Every 3 years 3rd party Testing
facility