HP Performance Optimized Datacenter (POD) 240a Site Requirements Guide
Appendix A: HP Site Assessment 26
Item Description Sign-off
14.
Recommendation
s
Following HP installation site visit, analyze the data
collected and prepare a report of findings. HP must
identify potential obstacles to installation and
recommendations for any additional testing or changes
to the installation plan.
Customer responsibilities:
Item Description Sign-off
1. Point of contact
information
Provide HP with the name and telephone number of the
designated point of contact for the purposes of this
Service.
2. Service Listing
information
Provide all information required under this Service Listing
or reasonably determined by HP to be necessary to
deliver the Service, including without limitation, any
documentation (internal or external) regarding prior
plans or investigations that were used to identify
proposed installation site.
3. Timely
response
Provide a timely response (such as, in a time period that
does not adversely affect the HP scheduled performance
of the Service) to all requests for information by HP.
4. Access to
subject areas and
support areas
Provide HP access to all subject areas and support areas,
including the proposed installation site and any
mechanical or electrical infrastructure provided to
support the HP POD 240a.
5. Badge access
Provide HP badge access or an escort for the duration of
the site visit to facilitate required access to all necessary
areas.
6. Site
engineering
personnel
Customer site engineering personnel familiar with the
proposed installation site as well as personnel
responsible for the maintenance and support of the
existing infrastructure must be available to answer
questions.
7. Documentation
Provide HP copies of all available mechanical and
electrical system design documentation, including as-built
drawings and electrical single-line drawings. As
appropriate to the specific location, provide HP with
campus maps, building drawings, floor plans or other
relevant prints that will assist in the documentation and
evaluation of the proposed installation site.
8. Network
infrastructure
information
Provide HP information regarding the planned network
infrastructure connection points and pathways.
9. Permission for
Photographs
Grant HP permission to take photographs for report
illustration purposes.
10. Project
logistics
Site-specific project logistics arranged at the time of
scheduling. Failure to provide necessary authorizations
might limit the effectiveness of the Service and could, at
the discretion of HP, impact scheduling or result in the
postponement of the Service.