HP BladeSystem c-Class Site Planning Guide

Preparing for installation 62
Sample installation schedule
The following schedule lists the sequence of events for a typical system installation. For situations that
prevent following this type of schedule, consider using a milestone schedule.
60 days before installation
o Floor plan design completed and sent to Hewlett-Packard (if required to be an HP task)
30 days before installation
o Primary power and air conditioning installation completed
o Telephone and data cables installed
o Fire protection equipment installed
o Major facility changes completed
o Special delivery requirements defined
o Site inspection survey completed
o Delivery survey completed
o A signed copy of the site inspection and delivery survey sent to HP
o Site inspection and predelivery coordination meeting arranged with an HP representative to
review the inspection checklist and arrange an installation schedule
7 days before installation
o Final check made with an HP site preparation specialist to resolve any last minute problems
Sample checklists
Customer and Hewlett-Packard information checklist:
Customer information
Name: Phone:
Street address:
City or town:
State or province: Country:
Zip or postal code:
Primary customer contact: Phone:
Secondary customer contact: Phone:
Traffic coordinator: Phone:
Hewlett-Packard information
Sales representative: Phone:
Survey representative: Date:
Order number: Scheduled delivery date:
Sample site inspection checklist:
No.
Yes No Comment or date
Computer room