Compaq Parallel Database Cluster Model PDC/O1000 for Oracle8i and Windows 2000 Administrator Guide
Installation and Configuration 5-39
Compaq Confidential – Need to Know Required
Writer: Carol Tatick Project: Compaq Parallel Database Cluster Model PDC/O1000 for Oracle8i and Windows 2000 Administrator Guide Comments:
Part Number: 225083-002 File Name: f-ch5 Installation and Configuration.doc Last Saved On: 6/11/01 12:06 PM
Other Verification Tasks
Perform these other verification tasks:
■ Verify that Object Link Manager has been installed and is running.
■ Verify that the OPS_CMDISK symbolic link has actually been set.
To verify the Object Link Manager has been installed and is running, select the
Services icon in the Control Panel. Once there, look for Oracle Object
Service in the list of services and see if it is shown as “Started.”
If the Object Link Manager has been installed and the service is running,
verifying that the OPS_CMDISK symbolic link has been set can be done by
running the Object Link Manager to see if the link OPS_CMDISK is in the list
of links.
Power Distribution and Power
Sequencing Guidelines
It is recommended you connect most PDC/O1000 cluster components to a
Compaq power distribution unit (PDU). PDUs connect to an uninterruptible
power supply (UPS) or building power. The PDUs and UPSs are the only
cluster components connected to a building power source. If there is no UPS,
the PDU plugs into building power.
It is also recommended that you connect cluster components, such as servers,
storage subsystems, switches, and hubs, to two PDUs and UPSs so the cluster
components continue to operate if one PDU or UPS fails.