HP ProLiant SL4500 Series Setup and Installation Guide
Cabling and powering up the chassis 44
2.
Move the cable management arm to the right rack rail and align the tab for opposite side mounting.
3. Align and install the cable management arm on the right rack rail.
Powering up the system
1. Connect the power cables to the power supplies.
2. Connect the power cables to the power source (UPS or wall outlet) or to an installed PDU.
3. Press the Power On/Standby button on the node.
Power capping
The HP ProLiant SL family of products provides a power capping feature that operates at the server enclosure
level. The capping feature can be activated using a stand-alone utility called PPIC.EXE that runs in the
environment of one of the resident servers in the chassis to be power capped. After a power cap is set for the