Develop the Schedule
The following schedule lists the sequence of events for an ideal system
installation.
60 days before installation
Floor plan design completed and mailed to Hewlett-Packard
30 days before installation
Primary power and air conditioning installation completed
Telephone and data cables installed
Fire protection equipment installed
Major facility changes completed
Special delivery requirements defined
Site inspection survey completed
Delivery survey completed
Signed copy of the site inspection and delivery survey mailed to
Hewlett-Packard
Site inspection and predelivery coordination meeting arranged
with a Hewlett-Packard Site Preparation Specialist to review the
inspection checklist and arrange a solution delivery schedule.
Solution delivery date
Final check made with an Hewlett-Packard Site Preparation
Specialist to resolve any last minute problems