director 2/64 installation guide
2–70 director 2/64 installation guide
Installing and Configuring the Director 2/64
.
Figure 2–46: Connect the Fibre Channel cables
2. Connect device cables to ports and route the cables through the cable management
assembly at the bottom front of the director. Start with the center UPM cards
(cards 7 and 8) adjacent to the CTP2 cards and work outward. In addition, start
with the bottom port of each UPM card and work upward.
3. Bundle Fibre Channel cables from the director and other equipment (groups of 16
maximum), and secure them as directed by the customer.
4. Set the director online. For instructions, see “Set the Director Online” on
page 2–43.
Connect the Director to a Fabric
To attach the director to a multi-switch fabric, connect the director to an E_Port of
another director or switch. The E_Port to E_Port connection is referred to as an ISL.
Use these steps to fabric-attach the director and create an ISL:
1. Verify that the director is defined via HAFM. See “Enabling HAFM to Manage
the Director” on page 2–37.
1 Director 2/64
2 Fibre Channel cables
3 Workstation