director 2/64 installation guide

2–2 director 2/64 installation guide
Installing and Configuring the Director 2/64
Verify that there is space in the rack. The director is 9U (15.75 in) high. In
addition, 1U is required in the HP rack system/e and industry-standard 19-in racks
for the rail tray kit. Note that the tray provides 1U of space for cable management.
Verify that the rack is stable.
If applicable, obtain the necessary remote workstations or Simple Network
Management Protocol (SNMP) workstations. Workstations are customer-supplied
and connected through a corporate or dedicated LAN.
Verify that all other equipment installed in the rack is connected to a reliable
ground connection; do not rely on connections to a branch circuit, such as a power
strip.
Hewlett-Packard recommends securing the rack mechanically to prevent it from
tipping over during a natural disaster, such as an earthquake.
Items Required for Installation
Locate the following items before beginning the installation procedure:
Lift device (recommended)
NOTE: Hewlett-Packard recommends using the LIFT-O-FLEX 17000 SP 400 from R on I.
For more information, visit the R on I Web site at http://www.roni.com/.
•Director 2/64
An HP 9000, HP 10000, HP 11000, HP M-Series, HP rack system/e, or
industry-standard 19-in rack, or any rack with the following specifications:
A minimum depth of 24.5 in
19 in wide
A minimum opening size of 10U available (9U for the director and 1U for the
rail tray kit).
Two power outlets or different branches (for redundancy)
Torque driver with cross-tip bit (for setting 22 in/lb. of torque)
Fiber-optic protective plug—For safety and port transceiver protection, fiber-optic
protective plugs must be inserted in all director ports without fiber-optic cables
attached. The director is shipped with protective plugs installed in all ports.