HP StorageWorks M-series Rack Mount Kit Installation Instructions (AA-RQZPE-TE, July 2004)

Installation Instructions
16 M-series Rack Mount Kit Installation Instructions
Tips for Installing More than One Switch
Review the following tips.
Install the first Director 2/64 in the lowest position of the rack, allocated for
switches.
Consider leaving a space of 1U open at the top and bottom of the rack, to
allow easier cabling access.
If installing more than one switch, HP recommends installing an optional
Power Distribution Unit (PDU) in the bottom of the rack. HP ships two PDU
power cords with the Director 2/64.
Install additional Director 2/64s in position directly above one another.
Make sure to connect power cables as you install each individual switch.
Moving the Director 2/64
Use these steps to position the Director 2/64 next to the rack.
WARNING: Two people will need to work together to transfer the
Director 2/64 to the lift. Make sure the wheels of the lift cannot roll as you
transfer the Director 2/64 to the lift. Move the Director 2/64 slowly and
carefully onto the lift to prevent back and hand injury. Dropping the Director
2/64 could injure personnel or damage the equipment.
1. Position the lift device next to the Director 2/64.
2. Using a pallet jack, raise the pallet on which the Director 2/64 is mounted to
the same height as the top surface of the lift device.
3. Slide the Director 2/64 across from the pallet to the lift device.
4. Determine the appropriate rack-mount position. Remember that the Director
2/64 is 15.75 inches or 9 U high.