Using Maintenance Features
Execute an IPL
To use this option, follow the detailed steps in the hp StorageWorks edge switch 2/32
service manual Execute an IPL
CAUTION: The Ethernet connection between the HAFM server and Switch is
interrupted momentarily during an IPL.
CAUTION: An initial program load (IPL) is not intended for ordinary or casual use and
should only be performed if the control processor (CTP) card is suspected to be faulty.
Do not use this option unless directed by your support representative or if you need to
reset a failed CTP card. An IPL will disrupt port operations. Before using this option,
make sure administrators of device(s) attached to ports quiesce Fibre Channel traffic
through the Switch and take the device offline. Note that the CTP card is not a FRU. If
it fails, the Switch must be replaced.
If it is necessary for you to execute an IPL on the Switch, use the following steps:
1. Choose IPL from the Maintenance menu on the menu bar.
A dialog box displays confirming the IPL.
Figure 5–2: IPL Confirmation dialog box
2. Click Yes.
Choosing IPL from the Maintenance menu causes Ethernet connection between the
Switch and HAFM server to drop momentarily and the following to occur in the
Product Manager window:
• As the network connection drops, the Switch Status table on the Hardware view
turns yellow.
•The Status field in the table displays “No Link” and the State field displays the
reason for no link.
• A grey square displays in the status bar. Refer to Table 1–1 on page 1-32 for an
explanation of this status bar display.