6.1 HP IBRIX X9000 Network Storage System Installation Guide (TA768-96058, June 2012)

1. The blade you are installing is assigned the appropriate name from the template, plus the last
octet IP for a hostname. If necessary, you can change the hostname on the Verify Hostname
dialog box.
2. The Verify Configuration dialog box shows the configuration for this blade.
If the configuration is correct, select Accept and go to step 3.
NOTE: To change the configuration, select Reject, and the following screen appears.
Choose Select FM Again to reselect the Fusion Manager and use the template again. To
configure the node manually, select Enter FM IP and and go to “Configure the blade manually
(page 68).
Installing additional X9730 blades 65