HP Director Blade Installation Instructions (SALTA)
FC4-16IP components
Figure 18 FC4-16IP
2. Status LED1. Power LED
4. Port status LED3. FC Port
6. GbE ports 0–75. FC ports 0–7
FR4-18i components
Figure 19 FR4-18i blade
2. Status LED1. Power LED
4. Port status LED3. FC Port
6. FC ports 0–155. GbE ports 0–1
Verifying installation requirements
The installation takes less than 10 minutes. You will
need the following items:
• Replacement director blade
• Filler panel for each empty slot (ships with the
director blade)
• Electrostatic discharge (ESD) grounding strap
• Workstation computer
• Phillips screwdriver
• Small form-factor pluggable (SFP) transceivers, as
needed (must be ordered separately)
• Quad SFP (QSFP) transceivers, as needed (must
be ordered separately)
Page 12