Site Preparation Guide, Eighth Edition - Superdome HP 9000 Systems

Chapter 4
Pre-Installation Survey
Typical Installation Schedule
66
Typical Installation Schedule
The following schedule lists the sequence of events for a typical system installation:
60 days before installation
Floor plan design completed and mailed to Hewlett-Packard
30 days before installation
Primary power and air conditioning installation completed
Telephone and data cables installed
Fire protection equipment installed
Major facility changes completed
Special delivery requirements defined
Site inspection survey completed
Delivery survey completed
Signed copy of the site inspection and delivery survey mailed to Hewlett-Packard
Site inspection and pre-delivery coordination meeting arranged with a Hewlett-Packard
representative to review the inspection checklist and arrange an installation schedule.
7 days before installation
Final check made with a Hewlett-Packard customer engineer to resolve any last-minute problems