4. The Description column displays the operation that was run. The Descriptions are explained
below.
ExplanationDescriptionCode
Initial copy began.PAIR START4710
Initial copy completed and pair status changed to SMPL.PAIR END4720
Pair split operation began.PSUS START4730
Pair split completed and pair status changed to PSUS.PSUS END4740
Pair resync operation began.COPY(SP)/COPY START4750
COPY(RS-R)/RCPY START
Pair resync operation completed and pair status changed
to PAIR.
COPY(SP)/COPY END
COPY(RS-R)/RCPY END
4760
The pair was deleted and status changed to SMPL.SMPL(PD) DELETE4780
The pair was suspended and pair status has changed to
PSUE.
PSUE SUSPEND4790
The copy has terminated abnormally for reasons other than
above.
COPY ABNORMAL END47D0
Initialization processing has begun.INITIALIZE START47E9
Initialization processing has terminated normally.INITIALIZE END47EA
Initialization processing has terminated abnormally.INITIALIZE ENDED ABNORMAL47EB
Related information
“View Histories window” (page 79)
Maintaining the system
Some maintenance tasks are a response to behavior discovered during system monitoring. Other
tasks are done to keep the system in tune with your changing requirements.
Related information
“Removing reserve attribute from a volume ” (page 55)
“Pair operations during system, device maintenance” (page 56)e
Removing reserve attribute from a volume
You can remove the reserve attribute from a volume.
Prerequisite information
The volume’s status must be SMPL.
Procedure 6 To remove the reserve attribute
1. Click Replications > Local Replications in the tree.
2. Click Reserve Volumes tab.
3. In the Remove Reserve Volumes window, select the volume and click Remove Reserve Volumes.
4. Enter a Task Name and click Apply
Maintaining the system 55