HP XP7 Getting Started Guide

NOTE: For safe and efficient maintenance operations, clearance (c) should be made as large
as possible. Actual clearances for installation should be determined after consulting with the
site/facilities manager, as the clearances can vary, depending on building conditions. Although
all disk chassis come pre-installed, up to 1420 mm of clearance may be required at both front and
back for a disk chassis replacement.
The figures in this section are not drawn to scale.
Single rack configuration
The following figure and table show the service clearances and floor load rating for a single rack
configuration.
Figure 7 Service clearances for a single rack system
*1 Clearance (a+b) is based on the floor load rating and the clearance (c). Floor load rating and
required clearances are shown in Table 9 (page 24).
*2 Clearance (d) is required over 300mm to open the front door. In the case that the clearance
(d) is less tan the clearance (a), give priority to clearance (a).
*3 Clearance (e) is required over 200mm to open the rear door. If clearance (e) is less than
clearance (b), give priority to clearance (b).
System specifications and requirements 23