HP XP7 Getting Started Guide

*2 Clearance (d) is required over 300mm to open the front door. In the case that the clearance
(d) is less tan the clearance (a), give priority to clearance (a).
*3 Clearance (e) is required over 200mm to open the rear door. If clearance (e) is less than
clearance (b), give priority to clearance (b).
Table 11 Floor load rating and required clearances for a two rack configuration (two DKC)
Required Clearance (a+b) mFloor Load
Clearance (c) mRating
(kg/m2)
C=1.4C=1.0C=0.8C=0.6C=0.4C=0.2C=0C=-0.3
00000000Over 700
00000000.2600
0000.10.10.20.40.6500
00.10.20.30.30.50.60.8450
0.20.30.40.50.50.80.91.2400
0.50.70.80.90.91.21.41.8350
1.01.21.41.51.71.92.22.6300
Notes:
1. Actual clearances for installation should be determined after consulting with construction specialist responsible for
installation building, as they could vary depending on the size/layout of the system and building conditions.
2. When various configurations of disk arrays are arranged in a row, clearance values based on the largest disk
array configuration should be used.
3. From the viewpoint of maintenance operations, it is suggested that Clearance (c) be made as large as possible.
Three rack configuration (left module)
The following figure and table shows the service clearances and floor load rating for a three-rack
configuration.
System specifications and requirements 27