Getting Started Guide

Site plan requirements and actions 22
Site plan requirements and actions
Completing a site assessment
HP requires a detailed site assessment prior to planning and preparing the customer site location for the HP
POD 20c. Consult with HP to schedule a site assessment.
A standard site assessment visit includes the following tasks:
Selecting an appropriate site for the HP POD 20c
Assessing the proposed site for:
o Measurements for clearances
o Infrastructure for the final solution
o Access to utilities
o Site pad
o Installation considerations, including locations for delivery trucks, large installation equipment (such
as cranes), and storage
o Electrical infrastructure
o Chilled water infrastructure
o Facility network and access control systems
Developing an engagement plan and verifying customer contacts
Discussing future development and growth plans
For a complete site assessment checklist, see "Appendix A: HP site assessment (on page 26)."
HP Site Preparation Drawing Package
After receiving a signed purchase agreement, HP provides detailed engineering drawings. These drawings
contain information to assist you and your MEP team to prepare the site for POD installation. If there are
areas of special interest, HP can work directly with your MEP team to provide additional assistance.
Zoning and permit requirements
You are responsible for compliance of the overall installation in accordance with all local and national
regulations, ordinances, codes, and the product specifications.
Project coordination
Your Project Manager must perform the following tasks:
Coordinate with all trades prior to installation to ensure that trade conflicts are resolved.
Coordinate the installation and integration of all systems.