HP Performance Optimized Datacenter 40c G2 Site Preparation and Requirements Guide Abstract This document provides site preparation guidance for the HP Performance Optimized Datacenter 40c G2 (HP POD 40c G2).
© Copyright 2012 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without notice. The only warranties for HP products and services are set forth in the express warranty statements accompanying such products and services. Nothing herein should be construed as constituting an additional warranty. HP shall not be liable for technical or editorial errors or omissions contained herein.
Contents Overview ..................................................................................................................................... 5 About this document .................................................................................................................................. 5 Safety and NEC compliance ....................................................................................................................... 5 Site assessment .........................................
Completing a site assessment .................................................................................................................... 23 HP Site Preparation Drawing Package ....................................................................................................... 23 Zoning and permit requirements ................................................................................................................ 23 Project coordination.....................................................
Overview About this document This document outlines the site preparation requirements for an HP Performance Optimized Datacenter 40c G2. The customer must provide a qualified architectural or consulting engineering team to generate site-specific documents for each HP POD 40c G2 installation, including final site drawings. The customer's site installation design must comply with all local and national regulations, ordinances, codes, and the specifications listed in this document.
Site assessment HP requires a detailed site assessment prior to planning and preparing the customer site location for the HP POD 40c G2. Consult with HP to schedule a site assessment. Site preparation Site preparation must be complete prior to the POD delivery to ensure a timely installation and commissioning. The site must meet all pad, power, and chilled water requirements. Site safety and security Each customer site must have its own standard safety and security requirements.
HP POD 40c G2 capacities HP POD 40c G2 capacity limitations The capacity limitations for the HP POD 40c G2 are separated into two categories: electrical power and mechanical cooling capacities. Both of these categories are interdependent and must be considered in conjunction with the overall customer requirements. Electrical power capacities (critical IT power) The electrical system of the HP POD 40c G2 has two main feeds, A and B, each rated at 800 A 415 VAC Wye 3-Phase.
Site requirements Site pad The structural design of the HP POD 40c G2 site pad must be based on the specific weight load of the complete POD solution with IT installed, as well as any additional equipment. During design calculations, HP recommends that you provide structural support along the entire perimeter of the POD and use the maximum allowable POD weight. Upon installation, the POD structure must be leveled to ≤ 0.5º.
End 1 view clearances shown Top view keep-out clearances shown (shaded areas indicate required clearances) Site requirements 9
Top view clearances shown Side view clearances shown Adequate space around the HP POD 40c G2 is necessary for airflow and cooling purposes. These minimum clearances provide room for door opening only. Consider additional space as necessary for your site. Safety and clearance area WARNING: Check for electrical distribution and transmission lines in, over, and under the construction site and maintain a safe working clearance from energized electrical lines.
Verify the following clearances prior to delivery: • • • Working distance clearance—Maintain a safe working clearance according to the local utility company or AHJ for each of the following items: o Buildings o Fences o Gate headers o Underground and overhead utilities Infrastructure clearance o Underground power conduits, excluding power, water, and drainage lines connected to the HP POD 40c G2 o Underground water lines, excluding power, water, and drainage lines connected to the HP POD 40c
Grounding feature Specification Grounding electrode conductor pad • • The grounding electrode conductor connection bus pad is located on the outside of the HP POD 40c G2 on the cold aisle adjacent to the power cabinet. The grounding pad must be connected to the grounding electrode system or building steel in accordance with Article 250 of the NEC or equivalent regional regulation.
Requirement Specification Connection 1.9 cm (.75 in) G Adapter to 1.9 cm (.75 in) FPS Hardness No greater than 40°fH (equal to 400 ppm of CaCO3) Conductivity 100 to 1250 μS/cm Organic compounds None Type of water Drinking water. Do not use de-mineralized or softened water. Instant water fill flow rate 0.6 lpm (0.16 gpm) Humidifier For the exact requirements, see the humidifier documentation. IMPORTANT: If your water is out of range, consult a water quality expert.
IMPORTANT: The chilled water system piping and heat exchangers must be drained completely, and then purged using compressed air when storing or transporting at or below freezing temperatures. IMPORTANT: Operating the chilled water system at the higher end of the acceptable range decreases the overall thermal capacity of the POD. Acceptable water quality specifications Water must be maintained per the following acceptable water quality standards. Parameter Range pH 8.
Piping materials Do not use the following interconnecting piping materials in a closed water system: • Oxidizing biocides • Aluminum components • Brass components with high levels of zinc • Non-stainless steel iron components • PVC IMPORTANT: Even though some PVC grade piping materials are designed to handle the expected water pressure, the use of PVC materials should be reviewed and approved by the customer site engineers.
A 1N electrical configuration can be achieved by providing all required electrical feeders from a common power source and from common switchboards, and transformers. A 2N electrical configuration can be achieved by feeding parallel power paths from independent power sources, switchboards, and transformers. IMPORTANT: The required neutral must be provided as part of the 800 A 415VAC Y direct connection to the HP POD 40c G2.
Supported facility connections Environmental control system The ECS developed for the HP water-cooled POD is a stand-alone control system that requires no external connections with an external site system, BMS, public or private Internet sites, cloud, or wireless system to properly control the POD operation. The ECS includes Modbus TCP/IP connections through which a variety of data can be retrieved.
Top view shown Connection portal diameter Connection point Quantity 8 10.16 cm (4 in) portal Main electrical power feeds 5.
End view shown You must make the connections between the facility and the HP POD 40c G2. For configuration and installation instructions, consult with HP. Fire box The communication connections between the fire system and the HP POD 40c G2 are made through the fire box. End view shown You must make the connections between the facility and the HP POD 40c G2. For configuration and installation instructions, consult with HP.
Humidifier A dedicated water supply and approved drainage is required for the humidifier. For more information about the humidifier, see the HP Performance Optimized Datacenter 40c G2 Operation and Maintenance Manual provided with the HP POD 40c G2. The following image shows the location of the humidifier drain and water supply. End view shown IMPORTANT: Confirm with the AHJ that condensate water and rain water can be mixed in the same drainage.
It is your responsibility to facilitate these connections. HP can make these connections when specifically contracted to deliver these services and a Scope of Work has been drafted, reviewed, and signed for delivery services. The customer must provide an independent connection for each system listed in the following table. Alarm Description Fire prevention alarm Smoke is detected in the HP POD 40c G2.
Environmental considerations Environmental risks • Avoid placing the HP POD 40c G2 directly along a drainage path or in an area prone to flooding. • Verify that the HP POD 40c G2 is properly grounded in accordance with NFPA 70 and local and regional regulations (IEC for EMEA and APJ). Cold weather The HP POD 40c G2 requires a site chilled water supply and return, humidifier supply and drain, and condensate drains. Extreme cold weather can cause damage to the supply and drain lines.
Site plan requirements and actions Completing a site assessment HP requires a detailed site assessment prior to planning and preparing the customer site location for the HP POD 40c G2. Consult with HP to schedule a site assessment.
• Ensure that the site safety and security programs are properly administered. • Interface directly with the HP installation project manager to ensure clear lines of communication during the installation and commissioning processes. Site planning A comprehensive site plan assists with the site design (MEP) and ensures the best possible HP POD 40c G2 installation process.
• Assembly equipment locations HP POD 40c G2 lifting requirements WARNING: The only approved method for lifting the HP POD 40c G2 is the use of a spreader bar harness. Lifting an HP POD 40c G2 in any other manner can cause damage to the HP POD 40c G2 and void your warranty. HP POD 40c G2 storage requirements If the site is not ready for assembly and operation, determine a location for storage when creating the site plan.
• Access landings might be required to maintain the required access to the HP POD 40c G2 electrical panels.
Appendix A: HP site assessment HP POD 40c G2 site assessment checklist During a survey of the readiness of a proposed customer site for the HP POD 40c G2, the site is inspected for the following: • Accessibility of machinery for the transportation and installation of the HP POD 40c G2 • Assessment of the suitability of the site infrastructure for installing the HP POD 40c G2 and for supporting infrastructure preparation and serviceability requirements HP responsibilities Item Description Sign-off 1.
Item Description Sign-off Inspect the proposed installation site to confirm clearance requirements for installation and serviceability as per the HP POD 40c G2 specifications. Necessary clearances are determined, in part, based on the specific installation plans and infrastructure design. Location, orientation, and planned utilization can affect the necessary clearances. Consider future planning for the space around the installation site. Evaluate the HP POD 40c G2 installation site in 9.
Item Description 13. Chilled water infrastructure Determine the overall chilled water capacity, available flow rates, and supply/return temperature restrictions. Determine if there are any site specific requirements that mandate additional chilled water equipment, such as heat exchangers or mixing apparatus. Locate any existing or planned supply/return headers.
Item Description 9. Permission for Photographs Grant HP permission to take photographs for report illustration purposes. Sign-off Arrange site-specific project logistics at the time of scheduling. Failure to provide necessary authorizations can limit the effectiveness of the service and can, at the discretion of HP, impact scheduling or result in the postponement of the service. 11.
Appendix B: Preparing for delivery Pre-delivery tasks Allow adequate time for planning, scheduling, obtaining permits, design approval, inspections, and so on. Installation prerequisites Before installing the HP POD 40c G2, verify that the following prerequisites are met: • All components are delivered to the facility. • The HP POD 40c G2 and power distribution components are in the final location. • Facility power, water, and drainage are at the final location.
Item Description 7 When installing on an elevated surface, verify that the maximum height requirements for the circuit breaker actuator meet the local and national requirements. Verify that proper landings and the catwalk are planned for electrical cabinet access. Verify the planning for required egress routes for all HP POD 40c G2 personnel doors, cargo doors, and service area doors, including landings, the catwalk, and stairs.
Item Description 28 Verify the location of the EPO system external to the powerhouses, if applicable. Verify the location of the remote electronic monitoring system. 29 30 Sign-off Verify that tie-downs and other AHJ-required facilities for the HP POD 40c G2 and power containers are complete at least one week prior to arrival of HP-provided equipment.
Item Description 3 Verify that the HP Project Team coordinates with other site construction activities.
Appendix C: Regulatory compliance notices HP POD 40c G2 regulatory compliance The HP POD 40c G2 complies with the following regulatory standards.
Cables Connections to this device must be made with shielded cables with metallic RFI/EMI connector hoods in order to maintain compliance with FCC Rules and Regulations. Canadian notice (Avis Canadien) This Class A digital apparatus meets all requirements of the Canadian Interference-Causing Equipment Regulations. Cet appareil numérique de la classe A respecte toutes les exigences du Règlement sur le matériel brouilleur du Canada.
Glossary AHJ authority having jurisdiction APJ Asia Pacific Japan BMS building management system door A hinged portion of an enclosure that covers an opening. DX direct expansion ECS environmental control system EMEA Europe, Middle East, and Africa EPO emergency power off equipment A general term, including fittings, devices, appliances, luminaires, apparatus, machinery, and the like used as a part of, or in connection with, a modular data center. (Source: NEC.
labeled Equipment or materials to which has been attached a label, symbol, or other identifying mark of an organization that is acceptable to the authority having jurisdiction and concerned with product evaluation, that maintains periodic inspection of production of labeled equipment or materials, and by whose labeling the manufacturer indicates compliance with appropriate standards or performance in a specified manner.
Documentation feedback HP is committed to providing documentation that meets your needs. To help us improve the documentation, send any errors, suggestions, or comments to Documentation Feedback (mailto:docsfeedback@hp.com). Include the document title and part number, version number, or the URL when submitting your feedback.
Index A G about this guide 5 areas prone to lightning or power surges 22 assembly 31 assembly area 24 grounding requirements 11 C cables, FCC compliance 36 Canadian notices 36 capacity limitations 7 central facility infrastructure connections 17 clearance area 8, 10 cold weather considerations 22 connection portals 17 connections, additional 17 connections, facility 17 H HP site preparation drawing package 23 humidifier 20 I installation 24 installation equipment 24 IT cable portals 17 L lifting layo
R regulatory compliance identification numbers 35 regulatory compliance, HP POD 40c G2 35 S safety information 6, 10 security 6, 20 seismic activity 22 site assessment 6, 23, 27 site assessment checklist 27 site pad 8 site planning considerations 24 site preparation 6 site preparation checklist 31 site requirements 8 storage locations 25 supported facility connections 17 system capacity 7 T transformer and switchboard 16 U utilities 12 V vestibule specifications 25 W water supply 12, 13 weight 8 Z zon