Installation Instructions
Table Of Contents
- About This Document
- Contents
- 1 Changes in AAU3940 Installation Guide
- 2 Overview
- 3 Installation Preparations
- 4 Unpacking Check
- 5 Installation Process
- 6 (Optional) Installing an ODM
- 7 Preprocessing the AAU Maintenance Cavity
- 8 Lifting an AAU
- 9 Installing an AAU
- 10 Installing AAU Cables
- 11 Closing a Maintenance Cavity
- 12 (Optional) Installing a Cord Cover for an ODM
- 13 Adjusting the Horizontal Azimuth of an Antenna
- 14 Installation Checklist
- 15 Powering on an AAU
- 16 Appendix
d: Scenario in which an AAU is
installed together with an ODM on a
wall
e: Scenario in which an AAU is
installed on the top of a pole and an
ODM is installed on a wall
-
NOTICE
In all scenarios, AAUs are installed together with their bottoms facing downwards. The vertical
deviation angle of a support must be less than or equal to 5 degrees, as shown in the following
figure.
Figure 2-3 Vertical deviation angle of an AAU
(1) AAU
(2) Support (pole, top of a pole, or wall)
Requirements of Installation Scenarios
The following table describes the requirements for poles, walls, and tops of poles in the preceding
installation scenarios.
AAU3940
Installation Guide 2 Overview
Issue 01 (2015-01-15) Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.