Installation Instructions
Table Of Contents
- About This Document
- Contents
- 1 Changes in AAU3940 Installation Guide
- 2 Overview
- 3 Installation Preparations
- 4 Unpacking Check
- 5 Installation Process
- 6 (Optional) Installing an ODM
- 7 Preprocessing the AAU Maintenance Cavity
- 8 Lifting an AAU
- 9 Installing an AAU
- 10 Installing AAU Cables
- 11 Closing a Maintenance Cavity
- 12 (Optional) Installing a Cord Cover for an ODM
- 13 Adjusting the Horizontal Azimuth of an Antenna
- 14 Installation Checklist
- 15 Powering on an AAU
- 16 Appendix
Figure 2-10 Mounting kits for an ODM
(1) Attachment plate (2) Mounting bracket (3) Steel belt (4) Expansion bolt
2.5 Surge Protection Requirements
When an AAU is installed on a pole or the top of a pole, the AAU must meet the surge protection
requirements. Otherwise, surge protection measures must be taken.
A direct lightning strike protection measure must be taken (that is, a lightning rod is installed)
if AAU installation meets the following conditions:
l When the AAU is installed on a pole or the top of a pole, the distance between the top of
the pole and the top of the AAU is less than 30 cm (0.98 ft).
l The AAU is not installed within the protection range of the lightning rod.
When a lightning rod is installed near the AAU installation position, the following conditions
must be met:
l The distance between the lightning rod and the top of the AAU must be greater than 30 cm
(0.98 ft).
l The lightning rod must be properly connected to the onsite ground grid.
l The AAU PGND cable must be routed along the inner side of the pole and is connected to
the ground bar of the onsite ground grid.
l In addition to the above conditions, the lightning rod installation must meet other building
surge protection requirements.