Installation Instructions
Table Of Contents
- About This Document
- Contents
- 1 Changes in AAU3940 Installation Guide
- 2 Overview
- 3 Installation Preparations
- 4 Unpacking Check
- 5 Installation Process
- 6 (Optional) Installing an ODM
- 7 Preprocessing the AAU Maintenance Cavity
- 8 Lifting an AAU
- 9 Installing an AAU
- 10 Installing AAU Cables
- 11 Closing a Maintenance Cavity
- 12 (Optional) Installing a Cord Cover for an ODM
- 13 Adjusting the Horizontal Azimuth of an Antenna
- 14 Installation Checklist
- 15 Powering on an AAU
- 16 Appendix
Step 7 Securely bind the power cable to the binding bracket, as shown in the following figure.
Figure 10-17 Installing an ODM power cable
Step 8 Connect the other end of the ODM power cable to the external power equipment.
Step 9 Lay out the cables according to the instructions in Cabling Requirements, and use cable ties to
bind them.
Step 10 Label the installed cables according to the instructions in Attaching a Cable-Tying Label.
----End
10.5 Installing a Trunk CPRI Fiber Optic Cable Between an
ODM and a BBU
This section describes the procedure for installing a trunk CPRI fiber optic cable between an
ODM and a BBU when an ODM is configured.
Prerequisites
A fiber fusion splicer is available.
Context
A CPRI fiber optic cable to be installed is shown by illustration 3 in the following figure.
AAU3940
Installation Guide
10 Installing AAU Cables
Issue 01 (2015-01-15) Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
73