Commissioning the RT 7–19
RT installation
At this point, RT commissioning is complete, except for the RT to
HT tests described in section 7.8. You may or may not be able to
complete these tests, depending on whether or not other network
components are installed and operational. (See the test
requirements listed in section 7.8.)
Leave the RT powered on for testing and operation.
Perform the applicable tests described below if the newly installed
RT meets the listed requirements. If the RT/network does not yet
meet these requirements, perform the tests at a later time.
This test verifies the DS1 connection from the RT to the HT.
Requirements
The DS1 test described below requires the following:
The RT must be fully installed, commissioned, and in
contact with the EMS through the hub.
The HT must be operational and in contact with the EMS.
DS1 services must be configured and provisioned.
There must be no alarms present at the RT location.
A loopback connector must be connected to the input/out
port of the patch panel, as illustrated in figure 7-8.
Figure 7-8 RT to HT connection test setup
DS3
mux
Bit error
rate test
set
P
a
t
c
h
p
a
n
e
l
HT
RT
P
a
t
c
h
p
a
n
e
l
Hub site
Customer premises
Loopback
connector
QRSS (2E20-1
pseudo-random)
test pattern
DS1
DS3 DS3
DS1
Over the air
interface
T0009007
Test procedure
1. Connect a DS1 test set to the out/input points at DS1 RJ–48
port on the SSI board.
2. Select:
- QRSS (quasi random signal source) test pattern
- Recovered clock
- DS1 interface
3. Run the test for 1 hour.
7.8
RT to HT connection
tests
DS1 test