CIRCUIT SCHEMATIC HGRH
FIGURE 27 - Circuit Diagram HGRH
STARTUP INSTRUCTIONS
PRE-STARTUP CHECKS:

Electrically ground the unit. Connect ground wire to
ground lug. Failure to do so can result in injury or death.

Wire any field installed device such as a fan switch or
thermostat furnished by the factory in strict accordance
with the wiring diagram supplied with the unit. Failure to
do so could result in damage to components and will void
all warranties.
Before start-up, thoroughly check all the components.
Optimal operation of equipment requires cleanliness. Often
after installation of the equipment, additional construction
activities occur. Protect the equipment from debris during
these construction phases.
PRIOR TO THE STARTUP OF THE UNIT:
1. Ensure supply voltage matches nameplate data.
2. Ensure the unit is properly grounded
3. With the power off, check blower wheel set screws
for proper tightness and that the blower wheel
rotates freely.
4. Ensure unit will be accessible for servicing.
5. Ensure condensate line is properly sized, run,
trapped, pitched and tested.
6. Ensure all cabinet openings and wiring connections
have been sealed.
7. Ensure clean filters are in place.
8. Ensure all access panels are in place and secured.