User's Manual
Table Of Contents
- Table of contents
- 1 Notes on the document
- 2 Safety regulations
- 3 Product description
- 3.1 Characteristics of the DIB-R5
- 3.2 Components
- 3.2.1 Connection and control panel
- 3.2.2 VAC voltage supply
- 3.2.3 VDC voltage supply
- 3.2.4 Divider Unit (DIU)
- 3.2.5 Transmitting filter
- 3.2.6 TETRA Channel Unit (CHU)
- 3.2.7 Base Station Controller Unit (BSCU)
- 3.2.8 Interconnection Relay Unit (IRU) ‒ only in the case of a CHU expansion
- 3.2.9 Fan unit
- 3.2.10 Cavity combiner
- 3.2.11 Backplane
- 3.3 Interfaces
- 3.4 Wiring diagrams
- 3.5 Redundancy options
- 3.6 Scope of delivery
- 4 Operation
- 4.1 Safety measures and prerequisites
- 4.2 Switching on the DIB-R5 advanced
- 4.3 Function tests and operating surveillance
- 5 Service interruption
- 6 Recommissioning
- 7 Maintenance
- 8 Troubleshooting
6 Recommissioning
To recommission the product, you either have to connect the equipment rack to the
voltage source or switch it on, depending on the connection variant.
Recommissioning
For a new commissioning of DIB-R5 advanced, proceed as described in
Ä
Chapter 4.2
“Switching on the DIB-R5 advanced” on page 66.