Installation Guide

10
STEP 1: PREPARE FRONT FASCIA
Components Needed
Front fascia rails (D)
Front fascia splice insert (B)*
Fascia dams (foam)
Sealant tube & gun
Tools Recommended
FIRST: Lay the hanging channel and front
fascia parallel and evenly on a flat level non-
abrasive surface or slab. Make sure both front
fascia and hanging channel rails remain even
and flush together by taping every 15” across
span.
DO NOT USE PERMANENT MARKER
SECOND: Mark top of front fascia & hanging
channel every 12” from end to end with a
small pen/marker/pencil.
NOTE: Last space will be 12 ¾” opening to
allow for flange width on last panel.
DO NOT cut the hanging channel.
THIRD: 12” marks will be needed during
future STEPS for locking-in roof panels in the
correct location to ensure water-tight
connection.
DO NOT cut the hanging channel.