User Guide
IntelĀ® Integrated BMC Web Console Options IntelĀ® BMC And RMM4 User Guide
120 Intel order number H54847-001 Revision 2.8
7.4.2 Server Power Control Page
The Server Power Control page shows the power status and allows power/reset control of the
server. Figure 104 shows the details for an S1200BTL system.
For the Graceful OS Shutdown to function properly the OS must be ACPI aware and be
configured to do the shutdown without operator intervention. After a Graceful Shutdown has
been requested, if the system does not shut down as requested, the command cannot be
executed again for five minutes.
Figure 104: Remote Control Server Power Control Page on S1200BTL Platforms
The following power control operations can be performed.
Table 26: Remote Control Power Control Options on S1200BTL Platforms
Option Task
Reset Server Select option to hard reset the host without powering off.
Power OFF Server Select option to immediately power off the host.
Graceful Shutdown Select option to soft power off the host.
Power ON Server Select option to power on the host.
Power Cycle Server Select option to immediately power off the host, and then power it back on after one second.
Perform Action button Click to execute the selected remote power command.
Note: All power control actions are done through the BMC and are immediate actions. It is suggested to gracefully shut down the
operating system using the KVM interface or other interface before initiating power actions.