Installation Guide
RS70 Providence Rail System Installation Instructions 
RS70INST-1 (05/06/2019) 
Level Rail Section Application with Glass Balusters. 
Note: Glass Baluster application requires the  RS70 Providence series  rail sets specifically 
prepared  for  the  Glass  Balusters, along  with  the  appropriate  quantities of  balusters  (sold 
separately in packs of 5).  
Measure to determine baluster layout, cut rail sections to length. 
a.  Ensure newels or columns to which rail will be mounted are plumb and sturdy enough to 
support rail. If  newel/column  covers  are  used, ensure they have  blocking  at  each location where 
railing will be attached.  
b.  Measure span at top and bottom rail locations.
c.  The slots for the Glass Balusters are set for standard baluster spacing (with the variable 
spaces at the ends of  each  rail  section.  Hold one  section of the  Top/Bottom Common Rail  at  the 
bottom of the newels, and using the pre-marked locations as a reference, determine the best end 
baluster spacing by either locating a baluster directly at the center of the rail section, or the mid-point 
between two balusters as the center of the rail section. Once the best end baluster spacing is decided, 
mark  both  ends  of  the  rail  at  the  newels  and  square  cut  using  a  miter  box.  The  Top  and  Bottom 
Common Rail must be cut with exactly the same spacing, to ensure that the balusters will be plumb. 
Cut the Rail Top Cap to the required length. 
2.   Prepare aluminum reinforcements. 
a.  Cut the aluminum rail reinforcements to length, 1/4” shorter than the PVC rails. 
b.  Attach a mounting bracket to both ends of each Aluminum Rail Reinforcement, using four 
rail bracket screw 🅐. Lubricate the threads with soap to avoid binding and use a clutch type drill to 
avoid stripping screws.  
c.  Locate crush block(s) provided to the bottom Aluminum Rail Reinforcement, with spacing 
no greater than 36” from the end, or between Crush Blocks. 
d.  Drill a 3/16” hole through the Aluminum Rail Reinforcement and secure each crush block 
using one baluster screw 🅒. 
e.  Drill one additional 3/16” hole at each end of the bottom Aluminum Rail Reinforcement for 
drainage. 
3.   Install rail 
a.  Position  bottom  Aluminum  Rail  Reinforcement,  with  crush  block(s)  attached,  between 
newels or columns, centered in newel or column face, and secure each end with two rail attachment 
screws 🅑. 
b.  Position the  Bottom Common Rail  between  newels or  columns  and  seat  fully  down on 
bottom aluminum rail reinforcement. 
c.  Place a Tempered Glass Baluster into each slot. 
d.  Position the Top Common Rail over the ends of the Glass Balusters.  
e.  Seat remaining aluminum reinforcement into Top Common Rail. 