Installation Instructions
3. Before Starting the Installation
74
Site Prerequisites, Continued
Network port
distributors
Suitable electrical network port distributor should be available.
The exact location of the network port distributor, as well as the network
ports to reserve, should be known prior to installing the equipment.
Also, all the reserved ports on the network port distributors should be
qualified and tested before realizing the network connections with the
equipment.
Power supply
cable routing
Routing of AC or DC power supply power cable should be implemented as
prescribed by the local regulations regarding outdoor electrical installations.
Cable conduits
Appropriate cable conduits should exist for the routing of installed cables.
Grounding
Ensure the following:
To make a protective earth connection, use the grounding point located
close to the radio unit.
A grounding point (designated GND) should be located close to the
mounting position of the radio unit (0 to 2 m).
The grounding point must be connected to grounding cable at least 16 mm
2
diameter.
An appropriate, low-resistance grounding system as specified by the local
regulations is required.
The equipment will be connected to this grounding point, via the supplied
grounding cable. This can provides only partial protection against
Lightning-induced power surges. For more information regarding equipment
protection against Lightning-induced power surges please refer to the
following paragraph
Lightning and surge protection.
Lightning and
surge
protection
A: For Ethernet (SF/UTP) Cables:
Lighting surge protection device (LSP) is required to minimize possibility of
equipment damage to any equipment connected to the unit from lighting
induced surges.
B: Power Supply Cables (for radio unit direct powering):
A power surge protection device (PSP) is required to minimize possibility of
equipment damage from lightning induced surges or power supply surges.
For LSP and PSP details and instructions refer to please refer to item 1 of
Reference manuals on page 14.