5.6 Commissioning Finished
Commissioning the AP is now finished.
From this point on, the AP must be managed from the OMC-R Client, via the AP
Management System. If the AP has not been pre-provisioned in the AP Management
System, it must be configured before it is can enter service. See section 3 for information
about AP provisioning.
5.6.1 Finished On Site Commissioning
If commissioning has been done on site, return to the site installation procedure in section
6.2.3, 6.3.3 or 6.4.5, as appropriate.
5.6.2 Finished Advance Commissioning
If commissioning has been done in advance of sending the AP on site, it is advisable to
ensure that the AP will connect to its serving AP Management System prior to sending the
AP on site. To do this:
1) Verify that the AP has been pre-provisioned with a Site in the serving AP
Management System.
2) Provide the AP with an appropriate network connection. If the AP has been
commissioned to use IPsec, this means a network connection that will go via the
Security Gateway, which is likely to require connection of the AP to an external
network.
3) Power up the AP.
4) Use the OMC-R Client to verify that the AP has connected to its serving AP
Management System. The Site for the AP should have a green tick symbol against
its icon.
5) After verifying this, re-pack the AP so that it is ready for delivery to its intended site.