nano3G AP Installation Manual Commission a nano3G AP
N3G_INST_300 v8.1 for N3G_2.0.5 © ip.access Limited 2011 Page 40
5.6 Commissioning Finished
Commissioning the AP is now finished. 
From this point on, the AP must be managed from the OMC-R Client, via the AP 
Management System. If the AP has not been pre-provisioned in the AP Management 
System, it must be configured before it is can enter service. See section 3 for information 
about AP provisioning.
5.6.1 Finished On Site Commissioning
If commissioning has been done on site, return to the site installation procedure in section 
6.2.3, 6.3.3 or 6.4.5, as appropriate. 
5.6.2 Finished Advance Commissioning
If commissioning has been done in advance of sending the AP on site, it is advisable to 
ensure that the AP will connect to its serving AP Management System prior to sending the 
AP on site. To do this:
1) Verify that the AP has been pre-provisioned with a Site in the serving AP 
Management System. 
2) Provide the AP with an appropriate network connection. If the AP has been 
commissioned to use IPsec, this means a network connection that will go via the 
Security Gateway, which is likely to require connection of the AP to an external 
network. 
3) Power up the AP. 
4) Use the OMC-R Client to verify that the AP has connected to its serving AP 
Management System. The Site for the AP should have a green tick symbol against 
its icon. 
5) After verifying this, re-pack the AP so that it is ready for delivery to its intended site.