2 Installation Overview and Requirements
2.1 Installation Tasks
The tasks that must be completed to install a nanoLTE S60 AP and make it ready to provide
service are:
Pre-Provisioning
Site installation
These tasks can be completed in any order. In most cases, however, the most practical
approach is to pre-provision an S60 AP before site installation.
2.1.1 Pre-Provisioning
For information about nanoLTE AP pre-provisioning, see the nanoLTE AP Configuration
manual [INST_43370].
This manual has no further information on AP configuration.
2.1.2 Site Installation
Physical installation of a nanoLTE S60 AP at its operating site, including providing the AP
with power and a suitable network connection. The network connection provides a backhaul
path to the NOS Server and EPC or S1 Gateway.
The network connection must also provide Internet access so that the S60 AP can the
services it needs at boot time, including NTP, the Redirector and the public CRL mirror.
If a nanoLTE S60 AP has been enabled for service prior to the site visit, the installation
engineer can make test calls immediately.
2.2 Mounting Options
The mounting options for the nanoLTE S60 AP are:
Wall mounted, by using the wall mounting holes on the back of the unit (suitable
pan-head screws must be sourced separately)
Free standing, on the supplied stand, which must be placed on a stable flat surface
The hardware installation instructions in section 3 cover both options.