Installation Instructions

© ip.access Ltd
COMPANY CONFIDENTIAL 110#010XA_GDE.doc
- 13 -
2) Position the bracket on the wall and mark the position of the four screw holes. The top
of the bracket
MUST
be positioned uppermost. Ensure that the bracket is level and
sufficient clearance is maintained to allow the unit to be located on the bracket (at
least 80mm from the bracket to the top of wall and 120mm from the side of the
bracket to a side wall). See the diagram below.
80mm min
120mm min
Figure 6 Positioning mounting bracket
3) Drill the four holes in the positions marked in step 2 and insert the wall plugs (if
required). Fix the mounting bracket securely to the wall. The bracket is designed to
allow the nanoBTS unit to be mounted with the connections either to the top or bottom
of the unit.
4) Slide the nanoBTS onto the bracket and ensure that the retaining spring engages into
the indent at the rear of the unit.
5) Record the MAC address from the label against the correct location of the nanoBTS
in the site configuration plan.