3" Top Caps Manual

GROUND MOUNT INSTALLATION MANUAL - 6© 2019 IRONRIDGE, INC. VERSION 2.8
3. PLACE RAILS
A. ATTACH HARDWARE
On the ground, attach Rail Connector brackets to rail by
sliding 3/8”-16 bonding bolts into side slot. Space out to


Tape ends of rail, to keep bolts from sliding out while moving.
B. FASTEN CONNECTORS
Center rails on cross pipes, leaving equal distance on
ends. Secure with Rail Connector hardware: 3/8”-16

Torque U-bolt nuts to 60 in-lbs and bracket to 21 ft-lbs.
Spacing between rails should align with module manufacturer
recommended clamping locations.
GROUNDING LUGS
Insert T-bolt in top rail slot and torque hex nut to 80 in-
lbs. Install a minimum 10 AWG solid copper or stranded
grounding wire. Torque terminal screw to 20 in-lbs.
Only one Grounding Lug required per continuous subarray,
regardless of subarray size (Unless frameless modules are used,
see Page 10).
If using Enphase microinverters or Sunpower AC modules,
Grounding Lugs may not be needed. See Page 11 for more info.
Grounding Lugs can be installed anywhere along the rail and in
either orientation shown.
Grounding Lugs are intended to for use with one solid or
stranded copper wire, conductor size 10-4AWG.
4. SECURE LUGS
A
B
U-Bolt
60 in-lbs
Bracket
21 ft-lbs
Hex Nut
(84 in-lbs)
Terminal Screw
(20 in-lbs)
Hex Nut
(80 in-lbs)