UFO Tilt Mount Installation Manual

TILT MOUNT INSTALLATION MANUAL - 5©
2016 IRONRIDGE, INC. VERSION 1.10
3. PLACE RAILS
4. SECURE LUGS
A. CONNECT SPLICES
Use Bonded Splices, when needed, to join multiple
sections of rail. Insert Bonded Splice 6" into rst rail and
secure with two self-drilling screws, spacing them about
1” apart and torquing to 20 in-lbs. Slide second rail over
Bonded Splice and secure with two self-drilling screws.
í Rows exceeding 100 feet of rail must use Expansion Joints.
í For XR10 and XR100 rails, insert screws along the provided lines.
í Refer to Structural Certication letters for rail splice location
requirements.
í Screws can be inserted on front or back of rails.
í If using Bonding Bolt Splices, refer to addendum (v1.0).
B. ATTACH SOUTH RAILS
Slide 1" long bonding bolt into side-facing rail slot. Mount
rail to pivot bracket of South Legs and loosely tighten nuts.
C. ATTACH NORTH RAILS
Slide 2.25" bonding bolt into side-facing rail slot. Mount rail
to top of North Legs. Tighten all 3/8” hardware to 250 in-
lbs once rails are square.
í Use a straight edge to ensure South and North rails are on the
same plane. An extra section of rail works well.
í Rails can mount on either north or south side of North Tilt Leg.
B
C
A
Torque to
20 in-lbs
6" Inside Rail
1"
Torque All
Hardware
250 in-lbs
Use Straightedge
to Square Rails
Insert T-bolt in top rail slot and torque hex nut to 80 in-
lbs. Install a minimum 10 AWG solid copper or stranded
grounding wire. Torque terminal screw to 20 in-lbs.
í Grounding Lugs are only needed on one rail per row of modules.
í If using Enphase microinverters, Grounding Lugs may not be
needed. See Page 9 for more information.
í Grounding Lugs can be installed anywhere along the rail and in
either orientation shown.
Hex Nut
(84 in-lbs)
Terminal Screw
(20 in-lbs)
Hex Nut
(80 in-lbs)