User's Manual Part 2

Chapter 4 Itron/Actaris Meter Installation
32 100G Datalogging Installation Guide - Direct Mount
2. Loosen the index mounting screws 1/2 to one turn. Slide the index to the left and off
the mounting screws and remove from the meter.
Set the index aside where it will not be damaged or fill with dirt, rain or snow. The
index will be mounted in the endpoint later in this procedure. Verify the index
mounting screws are 1/4" long and not corroded. If the screws are the correct length
and not corroded, retain for later use. If the original screws are discarded, use the
correct replacement screws (see Installation Prerequisites on page 8.)
3. Remove the old gasket, gasket residue, and dirt from the meter (if applicable). The
meter face must be free of gasket residue or dirt before you install the 100G
Datalogging Gas Endpoint.
To assemble the 100G Datalogging Gas Endpoint and index
1. Separate the 100G Datalogging Gas Endpoint housing from the cover by pulling the
cover straight out from the housing. Set the endpoint cover aside where it will not be
damaged or fill with rain, dirt or snow. The cover will be used later in this installation
procedure.