User's Manual

Installing the 2.4 GHz OpenWay Gas Module on a Sensus Mete
r
2.4GZ OpenWay Gas Module Installation Guide 23
2. Detach the index cover from the meter by removing the four screws holding it in
place.
3
4
1
2
3. Examine the index cover screws you just removed. Verify that they are 5/8-inch long
and are not corroded.
If the screws are 5/8-inch long and are not corroded, keep them for later use.
If they are an incorrect length or are corroded, dispose of them properly. Use 10
- 24 x 5/8-inch screws as described in Replacement Screws on page 21 instead.
TIP You can use the index cover you just removed as a temporary storage
location for screws.
4. Unscrew one index mounting screw completely.
5. Remove the other index mounting screw.
6. Set the index aside for the moment. Place it where it will not be damaged; get filled
with dirt, rain or snow; or fall to the ground or floor. The index will be used later in
this procedure.
7. Examine the index screws you just removed. Verify that they are 5/8-inch long and
are not corroded.