2. To receive corrected reads, connect the red wire to the GND 2/3 (ground) TB3 telemetry
output position (C). Connect the white and blue wires to the pulse output 2 position.
3. After completing the wiring connections, install a cable tie to the meter cable just below the
exposed colored lead wires on the cable insulation. Remove the excess cable tie using
hand-held side-cutter pliers. The cable tie performs as a cable strain relief to mitigate the
risk of destructive tension on the lead wires.
4. Tuck the three gel connectors and cable tie inside the module housing, as shown in the
placement illustration and schematic.
Cellular 500G Module Remote Mount Installation Guide 4 Specific Meter Manufacturer Installation
October 11, 2021 815-0622-00 REV 000 Itron, Inc. Page 62 of 99