How To Guide

Commercial Installation Guideline Page 2 of 4
ITEC II05042011
Concrete Testing
Moisture Testing: It is the responsibility of the flooring contractor and the installer to confirm all concrete
substrates, both old and new, for moisture transmission using the Calcium Chloride Moisture Test
according to ASTM F-1869. Moisture vapor transmission should not exceed the recommended levels of 8
lbs. or less per 1,000 sq. ft. in 24 hours. This test should be performed and documented prior to
installation. A second testing option determines relative humidity in concrete floor slabs using In-Situ
Probes, which should be less than 90% RH per ASTM F-2170 before, during and after installation. These
acceptable moisture readings are only applicable when using iGrip adhesive.
PH LEVELS: PH must be between 5 and 9
Floor Preparation
Remove all foreign substances such as wax, grease, dirt and any substance or chemical that
could interfere with a good bond.
Fill all holes and cracks with a latex fortified Portland cement based patching compound. IVC US
only recommends use of latex fortified Portland cement based products as a satisfactory
patching or leveling compound.
IVC US recommends priming the floor with FLEX-PRIM Acrylic Latex Primer to prevent over
absorption of adhesives, contain dust, and to insure a better bond of adhesive to the subfloor.
Inspect all material prior to installation. Report any defects to the location where the flooring was
purchased
iv
.
Recommended adhesive and seam sealer
iGrip Adhesive infuze seam sealer FLEX-PRIM Acrylic Latex Primer
Trowel Specifications
Application Spread Rate Type of installation
1/16"x 1/32" x 1/32" U Trow el
1.6mm x 0.8mm x 0.8mm U
Up to 350 sq. ft./gal
Up to 8.6 sq. meters/liter
Porous Substrate
1/16" x 1/32" x 5/64" U
trow el1.6mm x 0.8mm x
2mm U
Up to 400 sq. ft./gal
Up to 8.9 sq. meters/liter
Non-Porous Substrate
Trow el dimensions are
w idth x depth x spacing.