INSTALLATION INSTRUCTIONS
for Wood/Clad Wood Windows without Exterior Trim
or Nailing Fin (JII025)
Newer construction methods have led to an increase in air and water
tightness in buildings. This frequently leads to negative air pressure
inside the home, which can draw water through very small openings.
Our installation method integrates the window with the rough opening
by creating an air seal on the interior with low expanson foam.
Thank you for selecting JELD-WEN products. Attached are
JELD-WEN’s recommended installation instructions for metal clad
wood windows without nailing n or primed wood windows
without exterior trim. Read these installation instructions
thoroughly before beginning. They are designed to work in most
existing applications. However, existing conditions may require
changes to these instructions. If changes are needed, they are
made at the installer’s risk. For installations other than indicated
in these instructions, contact a building professional.
Not all window types may be installed into every wall condition in all
areas. Consult your local building code ofcial for applicable building
codes and regulations. Local building code requirements supersede
recommended installation instructions.
Please Note! This installation guide specically addresses installation
into block/masonry wall, sheathed wall and open-stud wall
construction. These instructions do not apply to bow and bay
windows and apply only to windows with a horizontal at sill.
Installations where the sill is higher than 35 feet above ground level,
or any product installation into a wall condition not specically
addressed in these instructions must be designed by an architect
or structural engineer. Failure to install windows into square, level,
and plumb openings could result in denial of warranty claims for
operational or performance problems.
Note to Installer: Provide a copy of these instructions to the building
owner. By installing this product, you acknowledge the terms and
conditions of the limited product warranty as part of the terms of
the sale.
IMPORTANT INFORMATION AND GLOSSARY
ROUGH OPENINGS
GLOSSARY
Backer Rod (backing material)
A material (e.g. foam rod), placed into a joint primarily to control the
depth of the sealant.
Buck
A wood framework attached to the masonry inside a window or patio
door rough opening.
Masonry Clip
A galvanized metal strap that secures the window to the structure.
Mulled Unit
Two or more window units structurally joined together.
Precast Sill
A pre-formed concrete block placed in the sill of a masonry/block wall
to support a window.
Shiplap
The layering method in which each layer overlaps the layer below it so
that water runs down the outside.
Estimated Install
Time for New
Construction
First Time: 4.0 hr.
Experienced: 2.5 hr.
Professional: 1.5 hr.
12
6
1
11
2
10
3
9
8 4
7 5
Buck
Sheathed Wall
Trimmer
studs
Header
Sheathing
Sill
King
stud
Cripple studs
FULLY SHEATHED WALL CONSTRUCTION
This installation guide specically addresses masonry/block wall, fully
sheathed wall and open-stud wall construction.
MASONRY/BLOCK WALL CONSTRUCTION
This installation assumes that
a framework of studs (often
called a buck) has already been
properly fastened and sealed
to the concrete/masonry wall
by a building professional.
The wall framing is covered by
sheathing and the window sits
inside the rough opening.

Summary of content (6 pages)