Installation Guide
INSTALLATION INSTRUCTIONS
for Pre-Hung Exterior Entry Doors (JII106)
5
PREPARE BUCK
PREPARE STUD-FRAMED WALL
4
5
Sealant joints
Liquid applied 
ashing
6. Cut two pieces of 
self-adhered ashing 
6" wide by the sill 
pan width + 3" long.
a. For continuous 
slab landings 
only, cut out the 
insidecorner.
b. Adhere the pieces 
of ashing to the 
inside corners. 
Stretch ashing 
as needed to 
cover corners and 
layat.
7. Smooth gaps or 
bubbles beneath 
self-adhered ashing 
with a J-roller 
(remove and replace 
if necessary).
8. Seal back corners of 
sill pan with sealant.
9. For step-down 
landings only, cut 
plastic drain screen 
to length of sill + 
2" and staple 1/2" 
below sill edge. The 
drain screen provides 
a path for air to 
dry any incidental 
moisture in the 
roughopening.
End of Stud-Framed Wall Instructions, continue with section 6, 
“INSTALL DOOR.”
FOR RETROFIT INSTALLATIONS
After removing the old door, remove sufcient siding to expose at least 
9" of intact building wrap. If damaged, apply new building wrap in a 
shiplap manner. Verify header and trimmer studs are structurally sound.
PREPARE BUILDING WRAP
Verify these steps are allowed by the building wrap manufacturer.
1. Trim building 
wrap ush with 
the edges of the 
roughopening.
2. If installing a drip 
cap, (recommended 
because this 
integrates the 
building wrap and 
drip cap to protect 
the structure and 
the product from 
incidental water) 
at the head, slit 
building wrap 6" 
at 45°. Tape up 
asshown.
3. Trim the sides 
sufciently to allow 
the nailing n to be 
mounted against 
thesheathing.
4. Apply spray adhesive/
primer to the sill 
pan and surrounding area. Follow manufacturer’s instructions for 
application methods.
5. Cut a piece of self-adhered ashing the length of the sill and apply 
over the sill pan as shown. The bottom of the sill pan should be 
completely covered by the self-adhered ashing. For step-down 
landings, fold ashing down as shown. For continuous slabs, trim 
ush with rough opening.
45˚
6"
Sill pan 
width
3"
6"
Discard 
(for 
continuous 
slab only)
Continuous Slab 
Landing
Sill pan 
width
3"
3"
Sealant
1"
1/2"
Step-Down 
Landing
Sill pan 
width
3"
3"
Note! This section applies to installations into a buck only. For 
installations into a stud-framed wall, begin with section 5, “PREPARE 
STUD-FRAMED WALL.”
1. Seal any joint larger than 1/16" in the buck and between the buck 
and the concrete/masonry with sealant.
2. Cover the buck and the surrounding concrete/masonry at the head 
and jambs and sill with liquid applied ashing as shown.
END of Buck Instructions, SKIP to section 6, “INSTALL DOOR.”