Instructions / Assembly

INSTALL SILL PAN FLASHING SYSTEM
3
Installation Instructions
for Vinyl Patio Doors with Integral Nailing Fin (JII006)
6
Landings
These instructions cover two patio door sill conditions: the step-down
landing and the continuous slab landing. The installation methods vary
slightly between landing types.
Prepare Sill
1. A pan ashing system
(as dened in ASTM
E-2112) is required
at the sill prior to
window/door product
installation. Always
allow water to drain
out of the pan and
onto the building wrap,
drainage plane or to
the exterior.
NOTE: Sill pans for step-
down landings will have a folded-down edge in the front to accept the
step-down landing.
Continuous Slab LandingStep-Down Landing
2. Apply a continuous
bead of sealant to the
interior of the upturned
leg and end dams of
the sill pan (if using a
rigid sillpan).
Shim the Sill
See Product Installation Tolerance Table for tolerances.
Unless installing into a
sill pan with a positive
sloped draining system,
shims should be aligned
as dened by the label
on the patio door or as
statedbelow:
Shims (1/4" maximum)
should be placed near
the exterior edge of the
sill pan.
Place one shim 2" from each side of the rough opening (if the rough
opening is sized correctly, this should be approximately 1 1/2"- 2" from
the corner of the patio door).
Shims should be no more than 8" on-center.
There should always be a drainage path to the exterior out of the sill pan.
Shims can be held in place with sealant.
Increased shim height may be needed or may interfere with bar/grill
alignment of adjacent windows/doors.
2"
8" O.C.