Instructions / Assembly

7
4
Landings
These instructions cover two wall system sill conditions: the step-down
landing and the continuous slab landing. The installation methods vary
slightly between landing types.
Prepare Sill
1. A pan ashing system (as
dened in ASTM E2112)
is required at the sill prior
to window/door product
installation. Always allow
water to drain out of the pan
and onto the building wrap,
drainage plane or to the
exterior.
NOTE: Sill pans for step-down
landings will have a folded-down
edge in the front to accept the
step-down landing.
2. Apply a continuous
bead of sealant to the
interior of the upturned
leg and end dams of
the sill pan (if using a
rigid sillpan).
Shim the Sill
See Product Installation Tolerance Table for tolerances
1. Unless installing
into a sill pan with a
positive sloped draining
system, shims should
be aligned as dened
by the label on the
wall system or as
stated below:
Shims (1/4"
maximum) should
be placed near the
exterior edge of the
sill pan.
Place one shim 2" from each side of the rough opening (if the
rough opening is sized correctly, this should be approximately
1 1/2"- 2" from the corner of the wall system).
Shims should be no more than 8" on-center.
There should always be a drainage path to the exterior out of the
sill pan.
Shims can be held in place with sealant.
Increased shim height may be needed or may interfere with bar/
grill alignment of adjacent windows/doors.
Continuous Slab LandingStep-Down Landing
2"
8" O.C.
Assembly and Installation Instructions
for Smooth-Pro
F-4500 Fiberglass Folding Wall System (JII-90076)
INSTALL SILL PAN FLASHING SYSTEM