Prepare the Site
This chapter describes how to prepare your site so that you can install a router, discussing the
following topics:
Rack Requirements on page 39
Clearance Requirements for Airflow and Hardware Maintenance on page 42
Site Environmental Requirements on page 43
Fire Safety Requirements on page 43
Power System Requirements and Specifications on page 44
Site Electrical Wiring and Cable Guidelines on page 49
Fiber-Optic and Network Cable Guidelines on page 49
Routing Engine Interface Cable and Wire Specifications on page 53
Site Preparation Checklist on page 54
Rack Requirements
The router must be installed in a rack. Many types of racks are acceptable, including
front-mount racks, 4-post (telco) racks, and center-mount racks, an example of which
appears in Figure 15.
The following sections describe rack requirements:
Rack Size and Strength on page 40
Spacing of Mounting Holes on page 41
Connection to Building Structure on page 41