Location requirements
General:
· All of the location requirements for the charging station in the "KeContact P20/P30
Installation manual" must be adhered to!
· When mounting the floor-mounted columns in parking spaces or parking garages, appro-
priate anti-collision protection must be provided by the customer.
Concrete foundation:
· The calculation, design and manufacture of the concrete founcation lies in the scope of
responsibility of the producer of the site.
· A horizontal, level and sound foundation is required for installation.
To ensure safe and permanent anchoring, we recommend creating a concrete founda-
tion:
65cm (L) x 50cm (W), depth = min. frost limit but > 40cm, frost-free.
Concrete: C30/37 LP for XC4, XD1, XF4 or C25/30 LP for XC4, XD1, XF2
reinforced concrete: BSt 500 S; BSt 500 M
· The base must permit the running off of any water that has entered the base.
· All cables must be laid precisely in the centre of the concrete foundation from the base
and must have an excess length of approx. 1.5 m for the remaining installation activities.
· During the production of the concrete foundation, the cables must be protected against
damage using appropriate measures (e.g., a protective tube). The protective tube must
have an excess length of approx. 25 cm above the concrete foundation.
· Mounting the column on asphalt is not allowed!
Anchoring to the base
The enclosed dowels must be used for anchoring (6 x Hilti HKD-ER compact dowels M8x30).
Technical data
M8
Anchorage ground Standard concrete with a strength
class of C20/25-C50/60 or greater
Recommended load Tension N (uncracked concrete) 4
Per dowel Transversal shear V (uncracked con-
crete)
3,9 kN
Required clearance 10,5
cm
Torque Tinst 8 Nm
Drill-hole diameter do 10 mm
Drill-hole depth h1 33 mm