User manual

2 / 2
|6| DIP-switch settings
Position of the DIP-switches DSW1/2
[DSW1]…configuration
[DSW2]…addressing
Amperage settings with DSW1
Example setting for 16A.
SETTING THE AMPERAGE (DSW1) (*1)
Curr
ent
D1.6 D1.7 D1.8
Figure
Min. cable
cross
section
10A
OFF OFF OFF
1.5 mm²
13A
ON OFF OFF
1.5 mm²
16A
OFF ON OFF
2.5 mm²
20A
ON ON OFF
2.5 mm²
25A
OFF OFF ON
4.0 mm²
32A
ON OFF ON
6.0 mm²
(*1) Preadjusted maximum current value for the EV charger (control pilot duty cycle).
…Indicates the position where to push down the DIP switch.
|7| General commissioning process
1. Remove all residual installation and connection materials from the connection
area.
2. Before
commissioning, check all screw and terminal connections for firm seating!
3. Check whether all unused cable glands are properly sealed with blind plugs or
dummy screw fittings.
4. Ensure that the voltage of the mains supply line is switched on.
After 15 to 20 seconds, the status LED must flash green slowly.
The device performs a self test every time it is switched on.
5. Perform the specified initial tests according to the locally applicable regulations
and laws.
6. Close the connector panel cover to the charging station.
7. Mount the housing cover.
Commissioning mode
The charging station can be placed into a commissioning mode for supporting the
initial system test. During this, a self test of the device is performed (interlocking,
contactor activation, current measurement, etc.) and the result is displayed.
After successful test without connected vehicle, the contactor is switched for limited
time in order to facilitate the initial tests. A normal charging procedure is not possible
in commissioning mode. The interlocking of the connector socket is activated to
prevent a cable from being plugged in.
Switching on the charging station in commissioning mode via the supply voltage leads
for security reasons in an error state (white-red-red-red) to prevent an unattended
activation.
Activating the commissioning mode
Set the DIP-switch DSW2.8 to ON.
Perform a reset of the charging station. To do this press the [Service
button] for 1 second.
The commissioning mode is now activated and is indicated by the orange
status LED (lights continuously).
You now have the option for approximately 5 min. to contact with standard
test probes using the measuring device ( e.g. Astaco® test probes from
BEHA) and to perform the necessary tests.
After 5 min. have elapsed, the contactor is deactivated in the charging
station is shut down.
Deactivating the commissioning mode
DSW2.8 = OFF
Set the DIP-switch DSW2.8 to
OFF again.
Perform a reset of the charging
station. To do this, press the
[Service button] for 1 second or
switch the power supply voltage
off/on.
The charging station starts up
again in normal mode and is
ready for operation.
|8| Closing the Wallbox
Housing mark
Tighten the four screws until the
mark on the connector panel
cover is even with the housing
surface.
The connector panel cover must
seal the housing properly.
Fitting the housing cover
Fit the housing cover at the top
and push the cover downwards
slightly.
Make sure that the housing cover
is seated correctly at the top in
the housing guides.
Cover screws
Secure the housing cover at the
bottom using the two cover
screws [S].
© KEBA 2014
Subject to alteration in the course of technical advancement. No guarantee is offered for the
accuracy of the information provided. All rights reserved.
All brand and product names are trademarks of their respective companies. Technical
information in this document is subject to change without notice.
Document: Revision 1.00 / Release date: 06.02.2014 / Article no.: 93408
KEBA AG, Postfach 111, Gewerbepark Urfahr, A-4041 Linz; www.kecontact.com