User manual

Installation
16 / 48
Installation requirements
Before beginning the installation, the installation guidelines must be observed.
Contact person on-site (for access to the mains disconnector in the electrical distribution panel
board).
The electrical connection (mains supply line) must be prepared.
Acclimation:
With a temperature difference of more than 15°C between transport and installation site, the
charging station should be acclimatized for at least two hours unopened.
The immediate opening of the charging station can lead to a formation of water in the inside
and can cause damages when switching on the device. A possible damage could also occur at
a later time after installation.
Ideally, the charging station should be stored at the installation site for a few hours. If this is not
possible, the charging station should not be stored outside overnight or in a vehicle at cold
temperatures (<5°C).
Tool list to handle KC-P20
The following tools are required for the installation:
Flathead screwdriver for mains supply terminals (blade width 5.5 mm)
Flathead screwdriver for terminals X1/X2 (blade width 3.0 mm)
Phillips head screwdriver PH2
Mounting tools for cable glands M16 (width across flats 20mm) and M32 (width across flats
36mm)
LSA+ insertion tool (optional)