User manual

Installation
25 / 48
4.4.2 Connecting the mains supply line
Running the mains supply line
Running the mains supply line
(surface cable routing)
Run the mains supply line from ABOVE
as shown in the figure.
[M]… cable sheathing
Running the mains supply line
Running the mains supply line
(flush-type cable routing)
The power supply cable must be run as
shown through the feedthrough/double-
membrane seal [DMS].
Make sure that the double-membrane
seal fits cleanly against the cable
sheathing.
Please observe:
Use of a suitable cable sheathing diameter of the supply line or increase of the cable sheathing
diameter by means of suitable seal adapter (see list "Scope of supply" for details about the
terminal range).
Feed the supply line (feed line from above) resp. double-membrane seals (feed line from be-
hind) sufficiently into the cable fitting. The cable sheathing must be visible in the connection ar-
ea.
The installation pipe or cable conduit with the feed line may not be screwed together in the ca-
ble fitting (feed line from above) or run through the double-membrane seals (feed line from be-
hind).
The feed line must be run straight through the cable fitting (feed line from above) resp. the
double-membrane seals (feed line from behind), in compliance with the bending radii (approx.
cable diameter times 10).
The cable fitting resp. double-membrane seals must be installed properly and screwed together
sufficiently.