4.7.2 Safety checks
Before the initial use, check the effectiveness of the safety measure(s) of the system according to the nation-
ally applicable regulations (e.g.:ÖVE/ÖNORM E8001-6-61, DIN VDE 0100-600:2008-06 "Checks,...")!
Electrical systems or devices must be checked by the installer of the system or device before their initial op-
eration. This also applies for the expansion or modification of existing systems or electrical devices.
However, it is essential that all conditions for the safety measures are observed.
Moreover, the following points are to be taken into account:
The checks (continuity of the connections of the protective conductor, insulation resistance, RCD (FI)
triggering current, triggering time,…) are to be performed for the expanded or modified part.
The measurement devices must comply with the national regulations!
(e.g.: DIN EN 60557 (VDE 0413) "Electrical safety in low voltage distribution systems up to AC 1000V
and DC 1500V“).
The measurement results are to be documented. A test report is to be created and saved before the
check.
4.7.3 Firmware update
The firmware of the charging station can be updated via the network connection or via the USB connection
[X5] (P30 only).
Follow the documentation with the firmware package to update the charging station.
You can download the latest firmware at www.kecontact.com (download area). A new firmware
can take into account modified standards or improve the compatibility with new electric vehicles,
for example.